Art Plaza West Tower Tops Off

Art Plaza Topped Off

Art Plaza Topped Off

Rising very quickly is the two story Art Plaza in the Arts & Entertainment district of Miami. The East Tower topped off at 34 stories in November while the West Tower recently reached the 34th floor.

A year ago at this time, foundation work was beginning on the site after the previous buildings were demolished on the site. In March 2018, the towers were starting to go vertical, starting with the East Tower.

The Melo Group developed Art Plaza is expected to be completed in mid 2019.

Previous construction photos of Art Plaza can be viewed here.

Art Plaza East Tower Tops Off

Art Plaza Under Construction

After reaching the 33rd floor two weeks ago, the Art Plaza East Tower has topped off at 34 floors. The West Tower is on pace to top off by the end of the year.

Art Plaza started going vertical in April of this year and has topped off very quickly as with other Melo Group projects.

With 667 rental units, construction is expected to be completed in 2019.

Previous construction photos of Art Plaza can be viewed here.

Art Plaza East Tower Close To Top Off

Art Plaza Construction

Art Plaza Construction

The 34 story two tower Art Plaza in the Arts and Entertainment district has reached the 33rd floor on the East Tower and is about to top off. The West Tower has reached the 26th floor and is 7 floors away from top off.

When we last looked at Art Plaza in September, the towers were on the 24th and 18th floor of construction. Vertical construction began in April with foundation work beginning at the start of the year.

Art Plaza, developed by Melo Group, will have 667 rental units and 15,000 square feet of retail space.

Previous construction photos of Art Plaza can be viewed here.

Canvas Miami Almost Ready To Open

Canvas Miami

Canvas Miami

Located in Miami’s Arts & Entertainment district, the 37 story Canvas Miami is almost ready to open to residents.

Construction began in April 2016 and started going vertical July 2016 before topping off in August 2017.

With 513 residential units, Canvas will have a 6,000 square foot rooftop restaurant and ground level retail.

Canvas was developed by NR Investments.

Previous construction photos of Canvas can be viewed here.

Melo Group's Art Plaza Reaches 24th and 18th Floor Of Construction

Art Plaza Under Construction

Art Plaza Under Construction

The under construction Art Plaza in the Arts & Entertainment district continues to rise quickly as the East Tower has reached the 24th floor and the West Tower reaches the 18th floor. Both towers will top off at 34 stories.

When we last looked mid July construction was on the 14th and 9th floor and the first glass was being installed. The glass installation is continuing on the lower floors with the exterior of the building starting to get painted.

At this pace, both towers should be topped off before the end of 2018.

Art Plaza will have 667 units with 15,000 square feet of commercial space.

Previous construction photos of Art Plaza can be viewed here.

Square Station Now Completed In Arts & Entertainment District

The Completed Square Station

The Completed Square Station

The two tower 34 story Square Station with 710 apartments is now completed in Miami's Arts & Entertainment District. 

Prices range from 1 Bed/ 1 Bath $1600, 1 Bed/ 1 Bath + den $1650, 2 Bed/ 2 Bath $1930, 2 Bed/ 2 Bath + Den $2100, 3 Bed/ 2 Bath $2420. 

Developed by Melo Group, construction began October 2016 and topped off September 2017. 

Melo Group is also developing the under construction Art Plaza across the street, which recently reached the 8th floor. 

Previous construction photos of Square Station since the start of construction can be viewed here.

New Tower Coming To Miami Arts & Entertainment District

Proposed Site in Red

Proposed Site in Red

J. Milton & Associates has applied to rezone a 1.7 acre site in the Arts & Entertainment District to build a tower with up to 550 units, according to The Real Deal.

The site was purchased for $7.3 million in January 2015 and is located between the nearly completed Canvas Condo and The Filling Station Lofts between NE 16 St and NE 17th St and NE Miami Pl and NE Miami Ct. 

Under current zoning, the developer can build up to 36 stories with 852 residential units, but only micro-units. Under new zoning they can build up to 550 units in the range of 750 - 1300 square feet.

Other buildings in the area include the nearly complete Square Station and the under construction Art Plaza.