The under construction 43 story Muze at Met Square is getting closer to completion since we last looked in November 2017. 

Originally called Avant at Met Square, the name has changed to Muze at Met Square. 

With 391 rental apartments in Downtown Miami, Muze will also have SilverSpot movie theater in the building along with restaurants and retail. 

Construction started August 2015 and topped off June 2017.

Previous construction photos of Muze at Met Square can be viewed here.

Avant At Met Square Tops Off

Avant At Met Square Topped Off

The 43 story Avant At Met Square has topped out in Downtown Miami.

Construction began August 2015 and is expected to be completed first quarter 2018.

The windows are almost installed and painting has begun on the exterior of the building.

Previous construction photos of Avant at Met Square can be viewed here.

Avant at Met Square Close To Topping Out

Avant at Met Square

Avant at Met Square

The 43 story Avant at Met Square is close to topping out in Downtown Miami. When we last looked the building just reached the 28th floor. 

Construction started going vertical in January 2016 and the project is expected to be completed by first quarter 2018.

Previous construction photos of Avant at Met Square can be viewed here.

 

Avant At Met Square Reaches 28th Floor

Avant at Met Square Construction

Avant at Met Square Construction

Avant at Met Square has reached the 28th floor of the 43 story building. When we last looked in October 2016, the building just reached the 15th floor.

The glass had been installed at the base of the building and is starting to go in at the lower portion of the residential tower. 

Avent at Met Square will have a 19 screen movie theater and amenites include resort style pool, wellness center and dog salon.

The building is expected to be completed first quarter 2018.

Previous construction photos of Avant at Met Square can be viewed here.

Avant At Met Square Reaches 15th Floor

Avant at Met Square

Avant at Met Square

Avant at Met Square is starting to grow taller since we last looked at the project in July.

The 42 story building will have two levels of retail, plus a luxury 19 screen movie theater. 

Construction is expected to be completed by first quarter 2018.

Previous construction photos of Avant at Met Square can be viewed here.

Avant at Met Square Construction Photos

Avant at Met Square

Avant at Met Square

After going vertical at the beginning of the year, Avant at Met Square is starting to rise on the residential portion of the 42 story building. 

Avant at Met Square is located across the street from the proposed 70 story Riverwalk East Development site.

Avant At Met Square Going Vertical

Avant at Met Square

Avant at Met Square

After a long delay preventing construction, Avant at Met Square is now going vertical in Downtown Miami. 

The project will be 42 stories with 391 residential units. 

The site is located across the street from the Epic East site which is supposed to start construction later this year.