1010 Brickell

1010 Brickell Reaches 41st Floor

1010 Brickell

1010 Brickell

1010 Brickell has reached the 41st floor of the 50 story building and is close to topping out.

Construction started in November 2014 and is expected to be completed by Fall 2017.

Previous construction photos can be viewed here.

1010 Brickell Construction Photos

1010 Brickell Construction Photos

1010 Brickell is currently on the 37th floor of the 50 story residential condo in Brickell. Construction has been moving quickly since we last looked at the project in January of this year. 

1010 Brickell is rising on what used to be parking garage and is located right next to the Metromover station. 

Read More

1010 Brickell Construction Updates

1010 Brickell Under Construction

1010 Brickell Under Construction

After building the parking garage, construction has started on the residential floors of 1010 Brickell.

The 50 story condo was designed by Sieger Suarez and developed by 13th Floor Investments and Key International.

 

1010 Brickell Construction Photos

1010 Brickell

1010 Brickell

Since we last looked at 1010 Brickell back in March, the site just added a crane and was in the process of starting the foundation pour. Fast forward to the end of July and the 50 story condo is currently on the 6th floor. The building is just a bit higher than the height of the parking garage that was previously there.

1010 Brickell is just one of many condos being built in the Brickell area at the moment.

Construction at 1010 Brickell

After demolishing the parking garage that was on the site in September 2014, construction at 1010 Brickell has progressed quickly. 

A crane has been added to the site and deep digging has been underway. 

The 50 story condo is located right next to the metromover and is only a block away from Mary Brickell Village. 

Construction At 1010 Brickell

1010 Brickell Secures $76 Million Construction Loan

The 1010 Brickell project developed by Key International and 13 Floor Investments received a $76 million construction loan, according to The Real Deal.

In September, demolition began on the parking garage on the site and now preliminary construction has begun on the 50 story condo.

Demolition Of Parking Garage For 1010 Brickell Now Underway

Since prep work started the beginning of September, workers began the demolition on Saturday. Workers have already torn down a big chuck of the garage. The garage should be down completely by early next week.